HomeGlossaryHAM (Hybrid Annuity Model)
Contract TypesHAM

HAM (Hybrid Annuity Model)

A highway PPP model where the government pays 40% of project cost during construction and the remaining 60% as annuity over 15 years after completion.

Quick answer

A highway PPP model where the government pays 40% of project cost during construction and the remaining 60% as annuity over 15 years after completion.


The Hybrid Annuity Model (HAM) is a public-private partnership contract structure for highway construction introduced by NHAI in 2016. It is designed as a middle ground between pure EPC (where the government funds everything upfront) and BOT-Toll (where the private party bears all financial and traffic risk). Under HAM, the government pays 40% of the project cost in five construction-phase milestone payments, and the private concessionaire finances the remaining 60%, which the government repays as semi-annual annuity payments over 15 years after the project is complete.

What is HAM in government procurement?

HAM was introduced after India's BOT-Toll programme ran into widespread difficulties in the early 2010s, with traffic projections proving overoptimistic and several highway concessionaires defaulting on their debt. BOT-Annuity, the predecessor to HAM, eliminated traffic risk but left the concessionaire financing 100% of the project during construction. HAM reduces that financing burden to 60%, making the model more bankable for Indian infrastructure companies.

Under HAM, the concessionaire does not collect tolls. NHAI retains all toll rights. Revenue to the concessionaire comes entirely from the government's annuity payments. The annuity is fixed at bid time and is paid semi-annually over 15 years post-completion, adjusted upward by a partial inflation index (typically linked to WPI). This eliminates traffic risk entirely for the concessionaire and provides predictable revenue.

Construction phase milestone payments are triggered as the concessionaire completes defined physical progress milestones, typically at 10%, 20%, 30%, 40%, and 50% progress, with the fifth milestone at substantial completion. Each milestone payment is 8% of the total project cost. The concessionaire must finance the balance between ongoing construction costs and received milestone payments, which is typically done through a combination of equity and bank project finance loans.

Maintenance obligations continue through the 15-year annuity period. Part of the annuity is performance-linked: if maintenance standards are not met during inspections, a portion of the annuity payment is withheld.

Why it matters for bidders

HAM is currently the most common bidded model for NHAI highway construction packages, alongside EPC. For contractors seeking highway business, understanding HAM's financial structure and the required project finance capabilities is essential.

The key operational challenge for HAM contractors is managing construction-phase cash flow. The 40% government payment comes in five tranches as milestones are achieved, but construction costs are incurred continuously. The gap between money spent and money received must be financed through equity infusion and bank credit. Under-capitalised firms bidding for HAM projects face a cash crunch during construction.

The performance-linked annuity component means that operations and maintenance quality during the 15-year period directly affects revenue. HAM concessionaires must maintain the asset to NHAI's specified road condition standards, failing which annuity deductions apply. This requires retaining an O&M capability or subcontracting it to a specialist operator throughout the annuity period.

Key rules and thresholds

Construction milestones: 5 milestones, each at 8% of the total project cost, totalling 40%. Annuity payment: 60% of project cost paid in 30 semi-annual instalments over 15 years, with a partial inflation adjustment. Maintenance performance: annuity deductions for roughness index (IRI) and other road condition parameters falling below specified thresholds on NHAI inspection.

How Bid India helps

Bid India puts HAM (Hybrid Annuity Model) to work inside your capture and proposal workflow.

Discover tenders

See Bid India in action

Book a demo and we will show you the platform using your actual contract data.