HomeGlossaryDispute Resolution Board
Dispute Resolution

Dispute Resolution Board

A Dispute Resolution Board (DRB) is a standing panel of independent experts established at project inception to assist in resolving disputes between the government and contractor on large infrastructure projects.

Quick answer

A Dispute Resolution Board (DRB) is a standing panel of independent experts established at project inception to assist in resolving disputes between the government and contractor on large infrastructure projects.


A Dispute Resolution Board (DRB) is a panel of independent technical and legal experts appointed at the start of a large government infrastructure contract to provide real-time, project-specific dispute resolution. Used primarily in FIDIC-based and large-value Indian infrastructure contracts (highways, metros, ports, dams), the DRB aims to resolve disputes at the construction stage before they escalate to costly arbitration.

What is a Dispute Resolution Board?

In large Indian government infrastructure contracts, particularly those funded by multilateral agencies (World Bank, ADB, JICA) or procured by NHAI, railways, or major port authorities, the FIDIC conditions of contract specify a three-member Dispute Adjudication Board (DAB) or Dispute Resolution Board. The DRB typically consists of three members:

  • A technical expert in the relevant engineering discipline
  • A legal expert in construction contracts
  • A senior professional with experience in both fields

The DRB is constituted before project commencement and visits the site periodically throughout the construction period. This familiarity with the project distinguishes the DRB from arbitration, the DRB members know the project, the site conditions, and the parties. This enables faster, better-informed decisions.

When a dispute arises, the parties first attempt to resolve it directly. If unsuccessful, either party may refer the dispute to the DRB. The DRB reviews submissions, may visit the site, conducts a hearing, and issues a decision within a defined time (typically 28-84 days under FIDIC). This decision is binding on both parties and must be implemented immediately ("pay now, argue later"). The losing party can express dissatisfaction and ultimately take the matter to arbitration, but must comply with the DRB decision in the interim.

Why the DRB matters for Indian government suppliers

The DRB provides a significant advantage over traditional arbitration: fast, project-familiar decisions that prevent work stoppages over disputes. In NHAI and large metro rail contracts, the DRB has successfully resolved disputes ranging from EOT claims to Extra Item rates without derailing project progress. Contractors working on FIDIC-based tenders should understand DRB procedures and ensure their project teams document disputes properly for DRB referral.

Example

On a World Bank-funded urban transport corridor project, the contractor and the government authority dispute a INR 8 crore claim for additional piling work ordered due to undisclosed soil conditions. The contractor refers the dispute to the 3-member DRB. Over 60 days, the DRB reviews geological survey reports, site inspection records, and the original design assumptions. The DRB issues a decision in favor of the contractor for INR 6.5 crore. The government is required to pay within 28 days while retaining the right to challenge through arbitration within 28 days of the DRB decision.

Frequently Asked Questions

Is the DRB mechanism used in standard central government contracts?

Standard central government contracts (CPWD GCC, DGW model forms) do not include DRB provisions. DRBs are typically found in: FIDIC-based contracts for large infrastructure projects, World Bank and ADB funded contracts (where DRBs are often mandated), NHAI EPC and HAM highway contracts, and large metro/railway construction contracts. The mechanism is still uncommon in smaller and routine government contracts.

Are DRB decisions final?

DRB decisions are binding on both parties immediately but are not final in the way an arbitral award is. A party can express dissatisfaction within 28 days and ultimately take the matter to arbitration. However, both parties must comply with the DRB decision while the dispute continues in arbitration. This "provisional finality" is what makes DRBs effective, it prevents the "park and dispute" behavior common in traditional government contract disputes.

How are DRB members appointed in Indian projects?

DRB members are typically appointed by mutual agreement of both parties from a pre-agreed list. Each party may nominate one member, and the two party-nominated members jointly select the third (chairman). For NHAI and externally-funded projects, the development bank may have specific requirements for DRB member qualifications. DRB member fees are shared equally by both parties.

What is the difference between a DRB and a conciliation committee?

A government conciliation committee is an internal mechanism aimed at administrative settlement. A DRB is an independent expert panel constituted under the contract for real-time construction-stage dispute resolution. DRBs issue formal decisions that are contractually binding; conciliation committee recommendations require internal government financial approval before payment.

How Bid India helps

Bid India puts Dispute Resolution Board to work inside your capture and proposal workflow.

Central government tenders

See Bid India in action

Book a demo and we will show you the platform using your actual contract data.