HomeGlossaryBill of Quantities (BOQ) Format
Tender Document ComponentsBOQ Format

Bill of Quantities (BOQ) Format

BOQ Format is the standardised spreadsheet or table structure provided in a government tender document where bidders must enter their unit rates to produce a complete financial bid.

Quick answer

BOQ Format is the standardised spreadsheet or table structure provided in a government tender document where bidders must enter their unit rates to produce a complete financial bid.


BOQ Format is the specific tabular structure, typically a locked or partially locked spreadsheet, provided within an Indian government tender document into which bidders must enter their unit rates against pre-listed work items or supply items to constitute a complete, comparable financial bid.

What is BOQ Format?

The BOQ (Bill of Quantities) is the listing of all work items with estimated quantities. The BOQ Format is the pre-structured data entry template provided within the tender that bidders fill in with their rates. On e-procurement portals like CPPP and GePNIC, the BOQ is embedded in the portal, bidders click into each cell and type the rate, and the portal automatically calculates item totals and the grand total, which becomes the evaluated price.

Government BOQ formats are typically structured with columns: Item No., Item Description, Unit of Measurement, Estimated Quantity, Rate (blank, bidder fills in), Amount (auto-calculated = Qty x Rate), and Notes. For multi-section projects, the BOQ may have separate tabs for civil, electrical, plumbing, and HVAC items.

BOQ format rules are specified in the ITB and on the portal: bidders generally cannot change item descriptions, add rows, modify quantities, or alter the format structure. Only the "Rate" column is editable. Some portals lock the format entirely and validate that rates are within reasonable ranges (flagging rates more than 25% above Schedule of Rates). Submitting a modified or non-standard BOQ format is grounds for bid rejection.

Why BOQ Format matters for Indian government suppliers

Bidders must use only the provided BOQ format. Common errors include: using a modified downloaded spreadsheet that has been accidentally altered, entering the total amount instead of the unit rate, skipping items with zero rates (which leaves them at zero, the government then executes those items at no charge, creating a dispute), and entering rates with currency symbols or text that cause portal validation errors. Always verify the calculated total on the portal before final submission.

Example

A civil contractor downloads the BOQ for a school construction project from the CPPP portal. The BOQ has 156 items across civil and MEP sections. The contractor fills in rates for all 156 items in the locked portal template. Before finalising, they notice Item 47 (paint) shows Rs 0 per sqm, they had accidentally pressed "0" instead of skipping to the next row. They correct it to Rs 85 per sqm. After all corrections, the portal calculates a grand total of Rs 4.28 crore. The contractor confirms this is within 5% of their internal estimate and submits the BOQ in Cover 2.

Frequently Asked Questions

What happens if I quote Rs 0 for an item in the BOQ?


A zero rate for a BOQ item means the contractor is offering to do that specific work at no cost. If the bid is accepted, the government can require execution of that item at the zero rate. Accidentally quoting Rs 0 for significant items is a common costly bidding error. Always verify every row before final submission.

Can additional items be added to the government's BOQ format?


No. The BOQ format provided in the tender is fixed. Extra items cannot be added by the bidder. If the bidder believes an important work item is missing from the BOQ, they should raise a pre-bid query. The government may issue a corrigendum adding the item. Otherwise, the contractor may need to include the cost of unlisted but implied scope items in the rates of related BOQ items.

What is a "provisional sum" in a BOQ?


Provisional Sum (PS) is a fixed amount included in the BOQ for work whose scope cannot be fully defined at tender stage but is anticipated. Typically shown as "Provisional Sum: Rs 5,00,000 for unforeseen utility relocation." The PS is included in the total for comparison purposes but actual expenditure against it requires separate instruction from the procuring engineer. Rates for provisional sum items are negotiated when the scope becomes clear.

How is the financial bid evaluated when BOQ rates are very unbalanced?


The TEC checks for unbalanced bidding by comparing each quoted rate against the Schedule of Rates benchmark. If item rates are grossly unbalanced (some items 50%+ above SoR, others 50% below SoR), the bid may be flagged and in extreme cases rejected, even if the total price is L1. The government wants fair item rates to protect itself if quantities change during execution.

How Bid India helps

Bid India puts Bill of Quantities (BOQ) Format to work inside your capture and proposal workflow.

Discover opportunities

See Bid India in action

Book a demo and we will show you the platform using your actual contract data.